Project Summary
From the client: This was a Lakeville client that we recently did a bathroom for as well. They were looking for a space to walk into from the garage where they could hang coats, put away shoes and not crowd the workspace in their kitchen. They wanted a variety of ways to hang their belongings and to create a clean, beautiful space – particularly by taking white cabinets all the way up to the ceiling. The end product was even better than imagined.
Date: January 08, 2018
Style: Contemporary Farmhouse
Project Type: Mudroom / Entry
Location: Lakeville, MN
Materials For Bathroom Remodel
Tile
Vanity
Shower Surround
Shower Glass
Countertop
Project Photos
About This
Project:
Honey-Doers started by building out into their over-sized garage for the space. This kept their house connected to the garage, while keeping the entryway separate from the kitchen. These clients really love heated floors, so the team installed those right away, using the same tiles these clients used in their bathroom remodel. Custom cabinets went all the way to the ceiling, creating a space for large hanging items (long jackets, snow suits, etc.) and to hang double rods in some areas. The clients also wanted hooks for guests to hang their coats on, including their youngest guests – grandchildren! Honey-Doers installed two set of hooks, with one row hanging low enough for children to hang their coats. This mudroom also included a window to let in lots of natural light, over-sized hardware that can be used to open doors while wearing gloves, and outlets in the closets in order to plug in small vacuums and other appliances.
These Lakeville clients thought of everything with the help of Shelly and the rest of the Honey-Doers team! When asked how they felt about the whole process/the Honey-Doers team, the client replied, “I love them! Every person who came through that door – I just adored them!”
Bathroom Renovation
The bathroom was updated with Schluter in-floor heat and rectangular tiles (Firenze Carrara Tile) installed along the floor and walls. The tiling had a marble gray finish, matching the tone of the countertops and contrasting the clean, custom cabinets surrounding the new Caldonia vanity.
Office Renovation
The office renovation required all new flooring, custom cabinets, and new countertops. The cabinets were Black Walnut. And the countertops were Tier 5, Rolling Jasmine Quartz which matched well with the hexagonal Carlos Silver tiles. Underneath the tiles, we installed Schluter Ditra-Heat flooring.
Office Challenges
Removal of the original floor revealed asbestos underneath. Remediation and contamination were required.
Bathroom Challenges
The challenge for the bathroom involved a rework of the ventilation system. There were issues with the exhaust fan’s ducts. We installed new venting on the roof and out of the side of the home.
Custom Layout & Framing
Framed an open living zone with distinct TV lounge and gaming space
Created a half bathroom with privacy and future shower rough-in
Added recessed alcoves for shelving and storage to reduce furniture needs
Durable, Stylish Materials
Installed water-resistant luxury vinyl plank flooring throughout
Used neutral color palette with warm wood accents for long-term appeal
Installed sound-insulated ceilings and walls between floors
Built-Ins & Finishing Touches
Designed and built a media wall with integrated cable/electrical routing
Added dimmable lighting zones to support different room uses
Painted and trimmed with premium materials for longevity
Project Timeline
Phase Duration
Highlights
Phase Consultation & Estimate
Duration
3 days
Highlights
On-site walkthrough and itemized quote delivered within 72 hours
Phase Design & Planning
Duration
1 week
Highlights
Layout options reviewed; fixtures and finishes selected
Phase Permits & Materials
Duration
1.5 weeks
Highlights
Permit approved and materials ordered to match timeline
Phase Construction
Duration
4 weeks
Highlights
On-time execution with weekly check-ins and walkthroughs
Phase Final Walkthrough
Duration
2 days
Highlights
Minor paint touch-ups and final client approval
- Project completed on schedule and within 2% of original estimate.
Homeowner Feedback
“We couldn’t be happier with our basement. The Honey-Doers team was communicative, professional, and incredibly respectful of our home. The quality of the work shows in every detail—and now we actually spend time downstairs!” Lisa M., Apple Valley Read More Reviews
Related Projects
St. Paul Remodelers Ready to Update Every Room in Your Home
Honey-Doers provides home remodeling and exterior services throughout St. Paul, Minneapolis, and beyond. Our Minnesota remodeling team is dedicated to delivering quality, professional remodels within reasonable budgets. We value honesty and communication, and we keep our clients in the know every step of the way.
Learn more with a call or connect with us online for a free estimate.
Inspired by this project?
Let's talk about what's possible in your home.
Let's Bring Your Vision to Life.
Our team is ready to transform your home. Let's start with a free consultation — no pressure, no obligation.
Reviews: 134